Preview for review. Items marked Check are waiting on a fact or an approval.
Secret Bay
A Waterfront villa structure rising, May 2026

Journal · November 2026

Construction update

Waterfront structures are rising; Cliffside is in design and sales.

Waterfront

The first Waterfront villa's foundation was completed in September 2026, and its superstructure is under way. Photographs from April and May 2026 show structures rising on lot 2 and foundations and reinforcement on lots 3 and 4. Completion of the collection is targeted for end 2027 to early 2028; timing for each villa is to be confirmed.

Cliffside

The six Cliffside villas were unveiled on 21 July 2026. Lots 1 and 2 are released for whole ownership and lot 4 for 1/10 shares.